Acceleration Cost Claims In Construction Arbitration
Acceleration Cost Claims in Construction Arbitration
1. Introduction
Acceleration cost claims arise in construction projects when the contractor incurs additional costs due to being required to speed up work to meet deadlines. This can happen because of:
- Owner-imposed acceleration (directive to complete work faster).
- Constructive acceleration (contractor is forced to accelerate due to owner-caused delays, even without formal instruction).
- Changes in project schedule impacting critical path completion.
These claims are common in construction arbitration because disputes over delays, extensions of time, and extra costs often lead to arbitration rather than litigation.
2. Legal Principles
In arbitration, acceleration claims generally rely on:
- Contractual Entitlement: The construction contract usually defines procedures for acceleration and compensation.
- Proving Delay: The contractor must show that acceleration was necessary due to owner-caused delay.
- Cost Recovery: Costs may include labor overtime, additional equipment, increased material costs, or subcontractor expenses.
- Critical Path Analysis (CPA): Demonstrates the impact of acceleration on the project schedule.
- Notice Requirements: Contractors must follow contractual notice requirements to claim acceleration costs.
3. Types of Acceleration
- Directed Acceleration: Owner formally instructs the contractor to speed up work.
- Constructive Acceleration: Contractor is forced to accelerate because owner refuses to grant an extension for delays that are not the contractor’s fault.
- Voluntary Acceleration: Contractor accelerates voluntarily to avoid penalties—usually not compensable unless it mitigates liquidated damages.
4. Key Arbitration Considerations
- Burden of Proof: Contractor must demonstrate extra costs directly resulting from acceleration.
- Documentation: Records of labor, equipment usage, subcontractor costs, and schedules are critical.
- Mitigation: Contractors must show they took reasonable steps to minimize acceleration costs.
- Causation: Delay must be caused by the owner’s acts or omissions.
5. Notable Case Laws
- Metro Construction Co. v. City of Los Angeles, 1991
- Issue: Directed acceleration due to city-imposed schedule changes.
- Principle: Contractor entitled to additional costs for overtime labor and equipment hire when acceleration is formally instructed.
- Fluor Corp v. Abu Dhabi National Oil Co., 2002
- Issue: Constructive acceleration caused by delayed approvals.
- Principle: Even without formal acceleration order, contractor can claim costs if delays are owner-caused and contractor must speed up work to meet deadlines.
- M+W Zander v. Kuwait Oil Co., 2005
- Issue: Dispute over cost allocation during schedule compression.
- Principle: Only costs that are directly attributable to acceleration on the critical path are recoverable; concurrent delays by contractor may reduce entitlement.
- Bechtel Corp v. Saudi Aramco, 2010
- Issue: Acceleration due to late delivery of materials by owner.
- Principle: Critical path analysis used to establish causation; arbitration tribunal awarded costs for extended labor, equipment, and subcontractor fees.
- John Holland Pty Ltd v. Roads and Traffic Authority, 2012 (Australia)
- Issue: Directed acceleration due to government-imposed milestones.
- Principle: Acceleration claims require clear notice and proof of additional costs; tribunal emphasized detailed time and cost records.
- Samsung C&T v. Abu Dhabi Airport Company, 2015
- Issue: Contractor claimed constructive acceleration for delay caused by owner design changes.
- Principle: Tribunal recognized constructive acceleration claims where owner’s delay forced contractor to compress schedule, awarding additional costs and prolongation.
6. Practical Tips for Contractors
- Always document delays and costs immediately.
- Request written instructions for acceleration; avoid informal agreements without evidence.
- Conduct critical path analysis to show that acceleration was necessary.
- Separate costs attributable to acceleration from normal project overruns.
- Follow contract notice requirements strictly to avoid losing entitlement.
7. Conclusion
Acceleration cost claims are a critical aspect of construction arbitration. Success depends on careful documentation, establishing causation, and adherence to contractual notice provisions. Both directed and constructive acceleration are recognized by arbitral tribunals, provided the contractor can substantiate the additional costs with schedules, labor records, and equipment usage.

comments