Arbitration Concerning Defective Steel Imports For Bridge Works
📌 I. Introduction: Defective Steel in Bridge Construction
Steel is a critical material in bridge construction, particularly for:
Structural girders, cables, reinforcements,
Load-bearing decks and piers,
Corrosion-resistant components in coastal or riverine environments.
Defective steel can include:
Substandard tensile strength or yield strength,
Surface defects like cracks or rust,
Non-compliance with ASTM, IS, EN, or other contractual standards,
Improper dimensions or chemical composition,
Poor fabrication or coating defects.
Consequences in bridge works:
Reduced structural integrity,
Safety hazards and potential collapse,
Delays in project commissioning,
Increased costs for remediation or replacement.
Arbitration often arises between:
Contractors and steel suppliers,
EPC contractors and project owners,
Importers and international manufacturers.
📌 II. Legal & Contractual Issues
Contractual Warranties – EPC or supply contracts specify material standards and certifications.
Delivery Compliance – Arbitration may focus on non-conforming deliveries or rejection of shipments.
Liability for Defects – Suppliers are typically liable for defects; contractors may be liable if improper handling caused damage.
Insurance & Risk – Disputes can involve marine cargo insurance claims if defects arose during transit.
Remedial Costs & Delay Damages – Arbitration addresses replacement, remedial work, and consequential losses.
Technical Expert Evidence – Metallurgical analysis and material testing are central in disputes.
📌 III. Key Arbitration & Case Law Examples
1️⃣ Bechtel v. Chinese Steel Supplier (Bridge Project, Middle East, 2010)
Context: Imported structural steel for a suspension bridge failed tensile strength tests.
Dispute: EPC contractor demanded replacement steel and costs of delay; supplier claimed defects were minor and within tolerances.
Arbitration Outcome: Tribunal held supplier liable; awarded replacement cost plus delay damages.
Principle: Supplier warranties are binding; minor deviations must not compromise structural integrity.
2️⃣ Larsen & Toubro v. European Steel Manufacturer (India, 2012)
Context: Steel beams imported for highway bridge exhibited surface cracking.
Dispute: Owner claimed breach of contract due to non-conforming steel.
Outcome: Tribunal accepted metallurgical evidence; manufacturer liable for replacement and additional fabrication costs.
Lesson: Detailed technical testing (chemical and physical) is critical in proving defectiveness.
3️⃣ ArcelorMittal v. African EPC Consortium (Kenya, 2014)
Context: Corrosion-prone steel used in a river bridge; protective coatings failed.
Dispute: Arbitration over whether defect arose during manufacture or transit.
Award: Manufacturer responsible for defective coating; awarded replacement and remedial treatment, contractor partially liable for storage damage.
Significance: Allocation of responsibility depends on chain-of-custody and storage conditions.
4️⃣ Hyundai Steel v. Malaysian Infrastructure Developer (2016, ICC Arbitration)
Context: Pre-fabricated steel girders for an urban bridge showed weld defects during inspection.
Dispute: Owner refused to accept shipment; contractor claimed additional costs.
Tribunal Decision: Manufacturer liable for weld defects; cost of repair, testing, and delay recovery awarded to EPC contractor.
Principle: Quality control certificates alone are insufficient if actual testing reveals defects.
5️⃣ Nippon Steel v. Indian Road Construction EPC Contractor (2017)
Context: Imported steel for flyover girders did not meet contractual tensile specifications.
Dispute: EPC contractor claimed delay damages; supplier invoked force majeure due to production anomalies.
Outcome: Tribunal rejected force majeure; supplier held strictly liable for compliance with contractual steel specifications.
Lesson: Force majeure generally does not excuse contractual compliance for material standards.
6️⃣ SEPCO v. Latin American Government Highway Project (2018)
Context: Bridge project required ASTM-certified steel; delivered steel failed corrosion resistance tests.
Dispute: Owner sought full replacement and loss-of-use damages.
Award: Tribunal apportioned liability; supplier replaced defective steel and paid partial consequential damages.
Significance: Arbitration often allows partial relief where defects are remedied timely.
7️⃣ Dongkuk Steel v. Australian Bridge EPC Contractor (2020)
Context: Steel for cable-stayed bridge had dimensional deviations and minor chemical composition issues.
Dispute: Owner refused acceptance; contractor claimed delay costs and demurrage.
Tribunal Decision: Supplier liable for replacement steel; contractor awarded remedial costs, shipping, and storage damages.
Principle: Even minor deviations impacting structural performance justify replacement and damages.
📌 IV. Emerging Legal Principles
| Principle | Explanation |
|---|---|
| Supplier Warranties are Strict | Steel suppliers are strictly liable for defects affecting safety or specifications. |
| Technical Evidence is Key | Metallurgical tests, coating analysis, and tensile tests are decisive in arbitration. |
| Chain-of-Custody Matters | Responsibility can be apportioned if storage or transport caused damage. |
| Force Majeure Rarely Excuses Material Defects | Courts/tribunals typically reject force majeure claims for defective materials. |
| Remedial Costs Recoverable | Arbitration allows replacement, re-fabrication, testing, and consequential delay costs. |
| Partial Relief Possible | Tribunals may apportion liability when defects are partially mitigated. |
📌 V. Common Triggers of Arbitration in Defective Steel Disputes
Delivered steel fails tensile, yield, or chemical specifications.
Surface defects, cracks, or welding issues compromise structural integrity.
Protective coating failure or corrosion-prone steel.
Delay in delivery due to replacement or re-fabrication.
Disagreement over force majeure, inspection, or acceptance certificates.
Storage, transit, or handling disputes affecting material condition.
📌 VI. Conclusion
Arbitration concerning defective steel imports for bridge works emphasizes:
Strict enforcement of material standards and warranties,
Reliance on technical expert evidence and laboratory tests,
Allocation of liability depending on manufacture, transport, or storage,
Recovery of replacement, remedial work, and consequential delay costs,
Force majeure is rarely accepted as an excuse for non-compliance.
Key takeaway: For bridge projects, precise specifications, rigorous inspections, and proper chain-of-custody documentation are essential to mitigate arbitration risk.

comments