Arbitration Regarding Breach Of Power Purchase Agreements In Solar, Wind, And Hydro Projects

1. Introduction: PPAs in Renewable Energy Projects

Power Purchase Agreements (PPAs) are long-term contracts between:

Project developers (solar, wind, hydro)

Distribution companies (DISCOMs) or government utilities

They typically cover:

Tariff structure and escalation

Project commissioning milestones

Grid connection and scheduling obligations

Force majeure and termination clauses

Payment security mechanisms (LCs, escrow accounts, or payment guarantees)

Breach of a PPA often leads to arbitration under the agreement’s dispute resolution clause.

2. Common Causes of Arbitration in Renewable Energy PPAs

(a) Delay in Project Commissioning

Failure to achieve Commercial Operation Date (COD)

Penalty disputes or termination due to delays

(b) Payment and Tariff Disputes

Late or non-payment by DISCOMs

Disagreement over tariff adjustments, escalation, or grid curtailment

(c) Termination Disputes

Alleged breach by either party leading to unilateral termination

Disagreement on compensation and damages

(d) Force Majeure Events

Natural disasters affecting generation

Policy changes affecting tariffs or grid operation

(e) Grid Availability and Curtailment

Disputes arising from limited evacuation infrastructure

Compensation for loss of generation

3. Issues Typically Framed by Arbitral Tribunals

Whether the project achieved COD under contractual conditions

Whether payment defaults constitute fundamental breach

Applicability and interpretation of force majeure clauses

Liability for delayed commissioning or curtailed generation

Quantum of damages or termination compensation

4. Legal Principles Governing PPA Arbitration

(i) Contractual Interpretation is Key

Courts defer to arbitrators’ interpretation of PPAs and related annexures.

(ii) Force Majeure Excuses

Delay or non-performance may be excused if covered by force majeure events.

(iii) Limited Judicial Interference

Courts do not revisit technical or commercial decisions of arbitral tribunals unless the award is perverse or illegal.

(iv) Payment Security Obligations

Utilities must honor escrow, LC, or other payment guarantees unless excused by contractual or statutory provisions.

(v) Termination Clauses

Unilateral termination must strictly comply with contractual conditions.

5. Important Case Laws (At Least 6)

1. NTPC Ltd. v. M/s. Maytas Infra Ltd.

Supreme Court of India

Principle:
Delay in commissioning is subject to assessment of extensions and force majeure clauses.

Relevance:
Applied in solar and wind PPAs where COD delays occur due to unforeseen circumstances.

2. Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran

Supreme Court of India

Principle:
Interpretation of contract clauses is within the jurisdiction of the arbitral tribunal.

Relevance:
Supports arbitrators’ assessment of PPA tariff disputes and breach determination.

3. Arosan Enterprises Ltd. v. Union of India

Supreme Court of India

Principle:
Even an erroneous interpretation of the contract is not sufficient to set aside an award unless unreasonable.

Relevance:
Ensures arbitral awards regarding PPAs are respected, even if alternative interpretations exist.

4. ONGC Ltd. v. Saw Pipes Ltd.

Supreme Court of India

Principle:
Breach of express contractual obligations constitutes patent illegality.

Relevance:
Invoked when developers fail to meet COD or operational obligations under PPAs.

5. Energy Watchdog v. Central Electricity Regulatory Commission

Supreme Court of India

Principle:
Change in law or regulatory orders may excuse performance.

Relevance:
Applied to renewable projects affected by tariff changes or grid curtailment due to regulatory directives.

6. McDermott International Inc. v. Burn Standard Co. Ltd.

Supreme Court of India

Principle:
Arbitrators are the final judges of facts and technical issues.

Relevance:
Critical in determining project performance, energy generation, and technical compliance under PPAs.

7. Nabha Power Ltd. v. Punjab State Power Corporation Ltd.

Supreme Court of India

Principle:
Contracts should be interpreted with commercial efficacy and intent.

Relevance:
Used in determining compensation and damages for breach or termination of renewable energy PPAs.

6. Typical Arbitral Findings in PPA Disputes

COD delays excusable if within force majeure or employer-caused delay

DISCOMs liable for delayed payments, subject to contractual security

Termination compensation based on net present value of remaining tariff payments

Losses due to grid curtailment are typically compensable if outside developer’s control

7. Practical Lessons for Renewable Energy PPAs

Define COD and milestone criteria precisely

Include detailed force majeure clauses for natural and regulatory events

Establish robust payment security mechanisms

Include clear curtailment and compensation mechanisms

Maintain documentation for commissioning, generation, and grid dispatch

Ensure dispute resolution clauses specify arbitration forum, seat, and governing law

8. Conclusion

Arbitration concerning breach of PPAs in solar, wind, and hydro projects emphasizes:

Precise contractual compliance for commissioning, generation, and payment

Allocation of risks for natural events, regulatory changes, and grid limitations

Technical and commercial expertise of arbitrators in renewable energy disputes

Indian courts consistently uphold arbitral awards enforcing PPA obligations while respecting commercial and technical assessments made by tribunals.

LEAVE A COMMENT