Concurrent Delay Analysis In Arbitration.
Concurrent Delay Analysis in Arbitration
I. Conceptual Overview
Concurrent delay arises where two or more delay events occur during the same period, at least one attributable to the employer (or principal) and another to the contractor. In arbitration—especially construction and infrastructure disputes—concurrent delay affects:
Extension of Time (EOT)
Liquidated damages liability
Prolongation costs
Disruption claims
Apportionment of responsibility
The central legal issue is:
If both parties contribute to delay during the same period, who bears the consequences?
II. Types of Concurrent Delay
True Concurrency – Two independent causes operate simultaneously and both affect the critical path.
Sequential but Overlapping Delays – Delays overlap but are not causally identical.
Dominant Cause vs Apportionment Models – Courts may identify a dominant cause or apportion responsibility.
Arbitral tribunals rely heavily on:
Critical Path Method (CPM) analysis
As-planned vs As-built comparisons
Window analysis
Time Impact Analysis (TIA)
III. Foundational English Law Principles
Construction arbitration in India and other Commonwealth jurisdictions often draws from English jurisprudence.
1. Prevention Principle
The employer cannot levy liquidated damages if it caused delay and failed to grant EOT.
This principle was discussed in Holme v Guppy, where it was held that a party cannot insist on performance if it prevented completion.
The doctrine evolved significantly in Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd, where employer-caused delay rendered the liquidated damages clause unenforceable if no EOT mechanism operated properly.
This case is frequently cited in arbitral awards dealing with concurrency.
IV. The Modern English Position on Concurrent Delay
2. Malmaison Principle
In Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd, the court held:
If there are two concurrent causes of delay, one employer-risk and one contractor-risk, the contractor is entitled to an extension of time but not necessarily to additional costs.
This has become a cornerstone in arbitral determinations of concurrency.
3. Apportionment Debate
In Walter Lilly & Co Ltd v Mackay, the court rejected strict apportionment in cases of true concurrency and reaffirmed that employer risk events justify EOT.
This case is often relied upon in international arbitration to argue against proportional allocation of delay.
4. Clarification in the UK Supreme Court
In North Midland Building Ltd v Cyden Homes Ltd, the Court of Appeal upheld a clause that contractually allocated concurrent delay risk to the contractor. It confirmed that parties may contract out of the Malmaison principle.
This case demonstrates that concurrency outcomes depend heavily on contractual drafting.
V. Indian Jurisprudence on Concurrent Delay
Indian courts frequently encounter concurrency issues in infrastructure arbitration.
5. Burden of Proof and Causation
In McDermott International Inc v Burn Standard Co Ltd, the Supreme Court emphasized that arbitral tribunals are masters of evidence and fact-finding, including delay analysis.
Tribunals must:
Establish causation
Examine critical path
Determine responsibility
6. Public Policy and Reassessment of Delay Findings
In Associate Builders v Delhi Development Authority, the Court held that re-appreciation of evidence is impermissible under Section 34 unless findings are perverse.
Thus, concurrency findings by arbitrators are rarely disturbed unless patently illegal.
7. Patent Illegality Standard
In Ssangyong Engineering & Construction Co Ltd v National Highways Authority of India, the Supreme Court clarified that erroneous interpretation of contract is not enough to set aside an award unless it shocks the conscience or ignores vital evidence.
This significantly protects arbitral determinations of concurrent delay.
VI. Approaches to Concurrent Delay in Arbitration
1. Full EOT Without Costs (Malmaison Approach)
Contractor receives extension
No prolongation damages
2. Apportionment Approach
Delay responsibility divided proportionally
Rare in English law but sometimes adopted by arbitral tribunals
3. Dominant Cause Approach
Tribunal identifies primary effective cause of delay.
4. Contractual Override
Contracts may state:
Contractor not entitled to EOT in concurrency
Employer delay does not relieve contractor delay
Such clauses are enforceable unless contrary to public policy.
VII. Interaction with Liquidated Damages
Concurrent delay impacts:
Whether LDs can be imposed
Whether time becomes “at large”
Whether prevention principle applies
If employer-caused delay exists and no EOT granted, time may become “at large,” eliminating LD entitlement.
VIII. Evidentiary Challenges in Arbitration
Concurrent delay cases often involve:
Expert scheduling evidence
Competing CPM analyses
Retrospective reconstruction
Window vs collapsed as-built analysis
Tribunals must determine:
Was delay critical?
Was delay excusable?
Was delay compensable?
Was there true concurrency?
IX. Key Legal Issues in Concurrent Delay Arbitration
Definition of concurrency
Critical path impact
Burden of proof
Prevention principle
EOT entitlement
Cost entitlement
Contractual risk allocation
Apportionment vs dominant cause
Tribunal’s discretion
Judicial review limits
X. Comparative International Arbitration Position
In international construction arbitration (FIDIC-based contracts):
Sub-Clause 8.4 (EOT) commonly invoked
Tribunals apply Malmaison-like reasoning
Some civil law tribunals apply proportional liability
Investment treaty tribunals also consider concurrency in delay-based damage quantification.
XI. Practical Drafting Considerations
To avoid disputes:
Define concurrency explicitly
Clarify whether EOT allowed in concurrency
Clarify cost entitlement
Specify methodology for delay analysis
Maintain robust project records
Provide clear notice mechanisms
XII. Conclusion
Concurrent delay remains one of the most complex issues in construction arbitration. The jurisprudence from Peak Construction, Malmaison, Walter Lilly, and modern Indian cases such as McDermott International and Ssangyong Engineering demonstrates:
Strong deference to contractual allocation of risk
Judicial restraint in reviewing arbitral findings
Importance of expert delay analysis
Ultimately, concurrency disputes are fact-intensive and heavily dependent on contract drafting, evidentiary quality, and arbitral interpretation.

comments