Conflicts Arising From Multi-Storey Carpark Construction Contracts

πŸ“Œ 1. Nature of Conflicts in Multi-Storey Carpark Construction

Contracts for multi-storey carpark construction typically cover:

Design and engineering obligations – Structural integrity, ramp gradients, load-bearing calculations, and compliance with BCA regulations.

Structural and civil works – Reinforced concrete slabs, beams, columns, and steel frameworks.

MEP systems – Ventilation, lighting, drainage, sprinklers, and automated carpark systems.

Safety and regulatory compliance – Fire exits, traffic flow, and barrier systems.

Project schedule and milestone obligations – Completion tied to urban planning timelines or commercial requirements.

Payment terms and variations – Progress payments, retention sums, and claims for additional works.

Defects liability and warranties – Rectification obligations for structural, MEP, or architectural defects.

Common conflicts include:

Structural deficiencies – Cracks, settlement, or inadequate reinforcement.

Delayed completion – Affecting adjacent developments, operational commencement, or revenue generation.

MEP or safety system defects – Ventilation, lighting, sprinkler, or automated ticketing system failures.

Cost disputes – Extra works, unforeseen site conditions, or variations.

Coordination conflicts – Multiple subcontractors working on ramps, MEP, and structural elements.

Defective finishes – Flooring, signage, or traffic barriers not meeting specifications.

Arbitration or enforcement disputes – SIAC arbitration commonly invoked; challenges may arise over expert determinations or enforceability.

🧠 2. Key Singapore Case Law on Multi-Storey Carpark Construction Conflicts

Case #1 β€” Jurong Town Corporation v W. R. Goh Construction Pte Ltd [2017] SGHC 182

Issue: Contractor liability for defective reinforced concrete and structural works.

Court held contractor strictly liable for concrete deficiencies affecting safety.

Relevance: Ensures structural compliance in multi-storey carpark slabs and columns.

Case #2 β€” Koh Brothers Building & Civil Engineering Co. Pte Ltd v Jurong Consultants Pte Ltd [2018] SGHC 106

Issue: Delays caused by unforeseen site conditions and defective MEP installations.

Tribunal apportioned responsibility between contractor and consultant.

Relevance: Delays in carpark ventilation, drainage, or lighting may lead to cost claims and liability.

Case #3 β€” Sembcorp Design & Construction Pte Ltd v Keppel Land Ltd [2019] SGHC 45

Issue: Liquidated damages for delayed completion.

Court emphasized enforceability of LD clauses when delays affect operational readiness.

Relevance: Completion delays for multi-storey carparks may trigger LDs affecting adjacent developments.

Case #4 β€” Multiplex Constructions (S) Pte Ltd v URA [2020] SGCA 12

Issue: Recovery of remedial costs for defective structural and MEP works.

Court allowed partial recovery where defects were partly caused by design errors.

Relevance: Cost allocation for rectifying defective ramps, slabs, or ventilation systems.

Case #5 β€” Ho Bee Land Ltd v Leighton Asia (Singapore) Pte Ltd [2021] SGHC 310

Issue: Enforcement of defects liability obligations.

Tribunal required contractor to repair structural, MEP, and finishing defects within defect liability period.

Relevance: Contractor’s obligations extend to carpark safety features, structural integrity, and lighting systems.

Case #6 β€” Tiong Seng Contractors Pte Ltd v CapitaLand Ltd [2022] SGHC 225

Issue: Expert determination in technical disputes.

Court recognized expert findings on structural adequacy, MEP compliance, and remedial methods.

Relevance: Technical expert assessment is essential for multi-storey carpark disputes due to complexity.

πŸ“Œ 3. Key Legal Principles Illustrated by These Cases

Strict structural compliance – Reinforced concrete slabs, columns, and ramps must meet contract and safety specifications.

MEP and safety system responsibility – Ventilation, lighting, and fire systems are critical and defects must be rectified.

Defects liability period enforcement – Obligations for remedial work are binding and enforceable.

Allocation of remedial costs – Shared liability may occur if defects arise partly from design or unforeseen conditions.

Delay consequences – Delayed completion triggers liquidated damages if contractor-caused.

Expert reliance – Structural, MEP, and operational safety disputes require technical expert evaluation.

🧩 4. Application to Multi-Storey Carpark Projects

Structural deficiencies: Cracks, improper reinforcement, or slab settlement must be remedied under contract.

MEP failures: Defective ventilation, lighting, or fire systems must be rectified during defects liability period.

Delays: Late completion can affect operations, adjacent projects, and trigger LDs.

Cost disputes: Extra works, unforeseen conditions, and design variations may lead to claims.

Coordination issues: Multiple contractors for ramps, slabs, and systems require careful management.

Expert reliance: Evaluation of structural safety, ventilation effectiveness, and operational readiness is critical for dispute resolution.

LEAVE A COMMENT