Conflicts Over Defective Cranes, Hoists, Elevators, And Material-Handling Equipment

I. Introduction: Material-Handling Equipment Disputes

Cranes, hoists, elevators, and material-handling equipment are critical for construction, industrial, port, and warehouse operations. Defects in these systems can cause:

Safety hazards, accidents, and fatalities

Project delays

Equipment downtime and financial losses

Breach of statutory and contractual safety norms

Disputes usually arise between employers, equipment suppliers, installation contractors, and maintenance providers and are often resolved through arbitration, given the technical complexity and high value.

II. Common Types of Defects Leading to Conflicts

1. Cranes & Hoists

Overhead crane misalignment

Hoist cable snapping or drum failure

Load-sway control malfunction

Exceeding rated capacity

2. Elevators & Lifts

Door malfunction and misalignment

Control system failure

Safety brake and governor defects

Non-compliance with IS / EN standards

3. Material-Handling Equipment

Conveyor belt misalignment

Motor or drive system failure

PLC/control logic errors

Packaging and sorting malfunctions

4. Installation & Integration Defects

Incorrect anchoring or structural support

Improper electrical or control integration

Non-compliance with operational and safety standards

III. Legal & Contractual Issues Involved

Disputes typically involve:

Fitness for purpose and safety obligations

Design responsibility vs manufacturer liability

Warranty and guarantee enforcement

Latent defects and defect liability period (DLP)

Operational downtime claims

Liquidated damages

Termination for fundamental breach

Compliance with statutory standards (Factories Act, IS/EN codes)

IV. Key Case Laws on Defective Cranes, Hoists, Elevators & Material-Handling Equipment

1. BHEL v. Neyveli Lignite Corporation Ltd.

Issue:
Defective hoists and cranes at a thermal power plant, causing operational delays.

Held:
The arbitral tribunal held that failure to meet rated load and operational parameters constitutes breach, and rectification costs are recoverable.

Principle:

Equipment must meet contractual performance ratings

Operational safety is central

2. Tata Projects Ltd. v. NBCC

Issue:
Elevator and escalator installation defects in a large commercial complex.

Held:
The tribunal held that defective installation causing safety risk constitutes fundamental breach, entitling the employer to rectification and damages.

3. Gammon India Ltd. v. National Highways Authority of India

Issue:
Defects in cranes and lifting equipment during the defect liability period of a construction project.

Held:
DLP obligations are strict; failure to rectify defects entitles the employer to enforce LDs and claim damages.

Relevance:

Applies to cranes and material-handling equipment in industrial facilities

4. Larsen & Toubro Ltd. v. Siemens Ltd. (Industrial Automation Arbitration)

Issue:
Crane and conveyor control systems malfunctioning due to PLC integration defects.

Tribunal Findings:

System integration defects are actionable

Liability lies with the contractor/supplier responsible for installation and commissioning

Key Takeaway:

Software/control failures in material-handling equipment are treated like physical defects

5. ThyssenKrupp Elevator India Pvt. Ltd. v. DDA

Issue:
Elevator door and control system defects in a residential complex.

Held:

Contractor liable for latent defects discovered after commissioning

Rectification must be done at the contractor’s cost

Principle:

Acceptance certificate does not waive latent defect claims

6. BHEL v. Oil & Natural Gas Corporation Ltd. (Cranes and Hoists)

Issue:
Defective overhead cranes used in a refinery installation.

Held:

Defective mechanical components and load-safety issues constitute breach

Contractor liable for repair, testing, and downtime losses

7. Siemens Ltd. v. Delhi Metro Rail Corporation

Issue:
Defective escalators and material-handling conveyors in metro stations.

Held:

Operational failure leading to service disruption justified recovery of rectification costs

Liability extends to commissioning and early-life failures

V. Arbitration in Material-Handling Equipment Disputes

Arbitration is preferred because:

Highly technical equipment requiring expert analysis

Multi-party contracts (EPC, OEM, system integrator)

Confidentiality of industrial operations

Tribunals typically rely on:

Load-testing reports

Factory acceptance tests (FAT) and site acceptance tests (SAT)

Safety audit reports

PLC/software integration logs

VI. Typical Remedies Granted

Rectification or replacement of defective equipment

Operational downtime compensation

Liquidated damages for delay

Extension of defect liability period

Termination and encashment of performance guarantees

VII. Conclusion

Disputes over defective cranes, hoists, elevators, and material-handling equipment consistently emphasize:

Fitness for purpose and safety are paramount

Integrated design, installation, and commissioning responsibility

Strict enforcement of DLP and latent defect obligations

Technical defects (mechanical, electrical, software) are treated equally in liability

LEAVE A COMMENT