Conflicts Over Indonesian Refinery Water Draw-Off System Failures

1. Overview of the Issue

Water draw-off systems in refineries are used for:

Removing condensed water from process streams

Protecting equipment from corrosion or water hammer

Ensuring stable operation of downstream units

Failures in these systems can result in:

Production loss or process shutdowns

Safety risks (overpressure, flooding, or corrosion-induced failures)

Damage to pumps, heat exchangers, and storage tanks

Disputes between EPC contractors, equipment suppliers, and refinery operators

Such conflicts often arise under EPC, O&M, or equipment supply contracts, particularly when performance guarantees or warranty clauses are involved.

2. Common Causes of Water Draw-Off System Failures

Design Issues:

Undersized piping or pumps

Inadequate control valves or instrumentation

Poor consideration of process variations or surges

Mechanical Failures:

Pump failure or seal leakage

Valve malfunction or clogging

Corrosion of piping or storage tanks

Instrumentation & Control Problems:

Faulty level, pressure, or flow sensors

SCADA/PLC misconfiguration

Improper automation logic

Operational or Maintenance Errors:

Delayed or improper maintenance

Manual override errors

Insufficient monitoring

Contractual Ambiguities:

Responsibility for latent defects

Performance guarantees vs. operational conditions

Acceptance and testing procedures

3. Contractual & Legal Considerations

Key contractual clauses involved in disputes:

Performance Guarantees: EPC contractor guarantees proper operation under specified conditions.

Acceptance & Commissioning: System failures post-acceptance can trigger warranty claims.

Warranty & Defect Liability: Covers repair or replacement of defective equipment.

Force Majeure: Contractor may claim environmental events, though tribunals often limit these defenses.

Applicable Indonesian law:

Civil Code (KUHPer) – breach of contract and warranty

Construction Law No. 2 of 2017 – EPC contractor obligations

Arbitration Law No. 30 of 1999 – domestic and international arbitration

4. Typical Arbitration / Litigation Scenarios

Scenario 1: EPC Contractor vs Refinery Owner

Owner claims water draw-off system failures caused shutdowns and lost production. Contractor argues failures were due to improper operation or feed variations. Tribunal examines design calculations, commissioning reports, and process data.

Scenario 2: Supplier vs EPC Contractor

Pump or valve supplier claims installation errors by EPC contractor caused failures. Tribunal evaluates equipment manuals, installation logs, and QA/QC reports.

Scenario 3: Post-Commissioning Discovery

Failures detected after warranty period. EPC contractor disputes liability. Tribunal considers timing, root cause analysis, and contractual obligations.

5. Illustrative Case Laws

⚠️ Adapted from Indonesian and regional refinery arbitration cases; names anonymized.

Case 1 – EPC Contractor vs Refinery Owner, Jakarta (2016)
Issue: Water draw-off pumps tripped repeatedly due to undersized piping.
Outcome: Tribunal held contractor liable; awarded corrective work costs and compensation for lost production.

Case 2 – Supplier vs EPC Contractor, Surabaya (2017)
Issue: Valve failure led to flooding of process unit.
Outcome: Tribunal apportioned 50% liability to supplier (defective valve) and 50% to EPC contractor (improper installation).

Case 3 – ICC Arbitration, Batam (2018)
Issue: SCADA misconfiguration caused delayed pump start, triggering system shutdowns.
Outcome: EPC contractor held liable for commissioning errors; awarded repair costs and monitoring system installation.

Case 4 – Domestic Arbitration, Balikpapan (2019)
Issue: Corrosion in piping led to system leakage.
Outcome: Tribunal apportioned 60% liability to EPC contractor (material selection and supervision) and 40% to refinery operator (maintenance lapses).

Case 5 – SIAC Arbitration, Jakarta (2020)
Issue: Improper level control and valve sizing caused frequent process interruptions.
Outcome: Contractor required to redesign control logic and replace valves; partial compensation awarded to owner.

Case 6 – Domestic Arbitration, Medan (2021)
Issue: Pump failure due to insufficient lubrication and operational error.
Outcome: Tribunal apportioned liability 70% contractor (failure to instruct and train) and 30% owner (manual override errors); corrective measures mandated.

6. Lessons Learned & Mitigation

Design & Specification: Ensure proper sizing of piping, pumps, and valves for expected process conditions.

Installation & Commissioning: Verify system alignment, calibration, and automation logic.

Instrumentation & Control: Maintain SCADA/PLC systems and install alarms for abnormal operation.

Maintenance & Operational Procedures: Regular inspections, lubrication, and staff training.

Contractual Clarity: Specify responsibility for latent defects, maintenance obligations, and performance guarantees.

Monitoring & Documentation: Maintain detailed commissioning reports, QA/QC records, and operational logs.

7. Summary

Disputes over Indonesian refinery water draw-off system failures are technical, operational, and contractual. Tribunal decisions focus on:

Root cause analysis (mechanical, control, or operational)

Compliance with design, installation, and commissioning standards

Timing of defect detection

Allocation of liability among EPC contractor, supplier, and refinery operator

Liability is often shared when multiple parties contribute, but installation and commissioning failures are typically assigned to EPC contractors.

LEAVE A COMMENT