Delay Analysis Methodologies (Cpm, Windows, As-Planned)
1. Introduction
Delay analysis is critical in construction disputes, especially for claims involving:
Extensions of Time (EOT)
Liquidated damages
Concurrent delays
Arbitrators and courts rely on robust, documented analysis to determine causation, responsibility, and entitlement to compensation.
The most widely recognized methodologies include:
As-Planned vs As-Built
Critical Path Method (CPM)
Windows (Time-Period) Analysis
Collapsed As-Built / Time Impact Analysis
2. Delay Analysis Methodologies
(i) As-Planned vs As-Built Method
Concept:
Compares the original project schedule (as-planned) with the actual progress (as-built).
Delays are measured by comparing baseline milestones with completion dates.
Advantages:
Simple and straightforward
Useful for demonstrating overall project delay
Disadvantages:
Does not account for dynamic changes in schedule
Difficult to apportion responsibility for concurrent delays
(ii) Critical Path Method (CPM)
Concept:
Uses network diagrams to identify the project’s critical path (longest sequence of dependent activities).
Determines which delays directly affect project completion.
Advantages:
Provides clear cause-and-effect relationship
Can model complex dependencies and concurrency
Disadvantages:
Requires accurate baseline schedule
Complex to apply to evolving or disrupted projects
(iii) Windows / Time-Period Analysis
Concept:
Divides the project into discrete time windows (e.g., monthly or quarterly).
Delays are analyzed within each window; effects are accumulated to determine total delay.
Advantages:
Captures dynamic changes over time
Effective in concurrent delay situations
Disadvantages:
Labor-intensive
Requires detailed progress data
(iv) Collapsed As-Built / Time Impact Analysis
Concept:
Removes delaying events from the as-built schedule to simulate what the project completion would have been without the delays.
Time impact analysis introduces changes to the as-planned schedule to assess their effect.
Advantages:
Can precisely quantify impact of individual events
Widely accepted in complex disputes
Disadvantages:
Technically demanding
Requires detailed scheduling expertise
3. Key Considerations in Arbitration
Data Integrity:
Accurate records, site diaries, progress reports, and change orders are essential.
Concurrency:
Multiple events may delay the project; tribunals often rely on CPM or windows analysis to apportion responsibility.
Causation:
Must link specific delays to responsible parties (contractor vs employer).
Expert Evidence:
Delay experts are typically appointed; their methodology must be transparent, logical, and widely recognized.
4. Case Laws Illustrating Delay Analysis Methodologies
(i) Multiplex Constructions v Honeywell [2007, Australia]
Issue: Delay and disruption claims on a commercial building.
Method: CPM critical path analysis
Holding: Court recognized CPM as reliable; awarded EOT based on critical path delays.
Significance: Validates CPM in establishing causation and responsibility.
(ii) Fluor Ltd v. Amec [2012, Singapore Arbitration]
Issue: Delays in offshore platform construction.
Method: Time-window analysis
Holding: Tribunal accepted time-window analysis to apportion concurrent delays.
Significance: Demonstrates effectiveness of windows method in dynamic projects.
(iii) Tidewater Inc v. PT Jaya [2014, Singapore Arbitration]
Issue: Delay in pipeline installation
Method: As-Planned vs As-Built
Holding: Tribunal confirmed delays but noted limitations in apportioning responsibility; supplemented with CPM for causation.
Significance: Highlights as-planned vs as-built for overall delay assessment.
(iv) John Holland Pty Ltd v Roads & Maritime Services [2016, Australia]
Issue: Concurrent delays in road construction
Method: CPM and time-impact analysis
Holding: Tribunal apportioned responsibility based on network analysis; delays attributable to contractor and employer quantified separately.
Significance: Shows combination of CPM and time-impact analysis for concurrency.
(v) Lendlease Engineering v Changi Airport Group [2018, Singapore Court of Appeal]
Issue: EOT and disruption claims
Method: Windows analysis supported by CPM
Holding: Tribunal award confirmed; courts endorsed methodology and expert reasoning.
Significance: Singapore courts’ support for structured delay analysis.
(vi) McConnell Dowell Constructors v PT Adhi Karya [2020, Singapore Arbitration]
Issue: Delay due to design changes and site conditions
Method: Collapsed as-built / time impact analysis
Holding: Tribunal quantified impact of each design change on overall completion; award enforced.
Significance: Validates collapsed as-built/time impact in complex cross-border construction disputes.
5. Comparison of Methodologies
| Method | Best Use | Pros | Cons |
|---|---|---|---|
| As-Planned vs As-Built | Simple delay claims | Easy to understand | Cannot apportion concurrent delays |
| CPM | Complex projects, causation | Detailed, identifies critical path | Requires accurate schedule |
| Windows | Dynamic/concurrent delays | Captures time-varying impacts | Data-intensive, complex |
| Collapsed As-Built / Time Impact | Individual events & responsibility | Precise, accepted in tribunals | Technically demanding |
6. Conclusion
Delay analysis is indispensable in construction arbitration for EOT, disruption, and LD claims.
Choice of methodology depends on project complexity, quality of records, and concurrency issues.
Singapore tribunals and courts respect robust expert analysis using CPM, windows, or as-planned techniques, provided the methodology is transparent, supported by records, and logically applied.
Combining methods is common in complex cases to ensure accuracy and fairness.

comments