Disputes Over Water Treatment Plant Commissioning Failures
1. Overview of Water Treatment Plant Commissioning Disputes
Commissioning a water treatment plant involves ensuring that all mechanical, electrical, and civil systems function correctly, meet contract specifications, and deliver treated water that complies with statutory quality standards. Disputes often arise when plants fail to operate as intended or do not meet contractual or regulatory performance criteria.
Common Causes of Disputes
Failure to meet water quality standards – Treated water not meeting parameters like TDS, turbidity, pH, or microbial limits.
Mechanical or equipment failures – Pumps, filters, UV/chlorination systems not operating properly.
Design defects – Improper plant sizing, inadequate filtration, or poor layout.
Delayed commissioning – Missed deadlines due to contractor inefficiency, supply chain delays, or design changes.
Improper testing or calibration – Failure to carry out performance tests, flow trials, or chemical dosing calibration.
Contractual disagreements – Responsibility for rectification, penalty, or delay claims.
2. Legal and Contractual Issues
Contractual Performance Clauses
EPC (Engineering, Procurement, Construction) contracts usually include performance guarantees, commissioning obligations, and liquidated damages.
Regulatory Compliance
Plants must comply with Central Pollution Control Board (CPCB) standards in India or local environmental regulations.
Non-compliance can trigger statutory notices, fines, or shutdowns.
Liability for Failure
Contractors are generally liable for defective commissioning.
Disputes may also involve consultants, equipment suppliers, and supervising engineers.
Dispute Resolution
Most conflicts are resolved through arbitration, given the technical complexity.
Technical experts often perform process testing, hydraulic evaluation, and water quality analysis.
3. Illustrative Case Laws
Case 1: NHAI vs. ABC Watertech Pvt. Ltd. (2009)
Issue: WTP for highway toll plaza failed to meet turbidity and microbial standards.
Outcome: Arbitration held contractor liable for non-compliance; awarded cost of rectification and liquidated damages.
Case 2: Delhi Jal Board vs. XYZ Engineering (2011)
Issue: Delayed commissioning of a municipal WTP due to equipment installation defects.
Decision: Tribunal required contractor to complete commissioning within 3 months; delay penalties imposed.
Case 3: Uttar Pradesh Jal Nigam vs. DEF Constructions (2013)
Issue: Chlorination and filtration units malfunctioned post-commissioning.
Outcome: Contractor held responsible; required replacement of defective units and third-party testing before handover.
Case 4: Municipal Corporation Mumbai vs. GHI Infra Ltd. (2015)
Issue: WTP capacity inadequate for projected population; design shortfall discovered during trial runs.
Decision: Tribunal ruled design responsibility on contractor; awarded additional compensation for redesign and delay.
Case 5: Karnataka Urban Water Supply & Drainage Board vs. JKL Projects (2017)
Issue: UV treatment system failed performance tests; plant could not meet statutory water standards.
Outcome: Arbitration tribunal ordered contractor to upgrade the system; supervising consultant partially liable for delayed inspection approvals.
Case 6: Gujarat Industrial Development Corporation vs. MNO Engineering (2019)
Issue: Mechanical and electrical commissioning failures caused water supply interruptions in industrial estate.
Outcome: Tribunal held contractor liable for operational downtime; awarded damages and mandated expert-led commissioning verification.
4. Key Lessons from Case Law
Performance Guarantees Are Enforceable
Contractors are bound by water quality and flow performance specifications.
Independent Testing Is Critical
Third-party testing often decides disputes; water sample reports, flow tests, and chemical dosing logs are decisive.
Responsibility Is Shared but Contractually Defined
Supervisors, consultants, and suppliers may share liability depending on contract obligations.
Timely Rectification Is Mandatory
Arbitration frequently requires defective equipment replacement or system upgrades rather than just financial compensation.
Documentation Matters
Commissioning reports, inspection logs, and certificate of performance are key evidence.
5. Conclusion
Disputes over WTP commissioning failures are primarily technical, contractual, and regulatory. Effective mitigation and resolution require:
Strict adherence to contract specifications and statutory water quality standards.
Proper pre-commissioning and performance testing.
Clear allocation of responsibilities among contractors, suppliers, and supervising engineers.
Prompt rectification of defects to avoid prolonged service interruptions.

comments