Frustration Doctrine In Arbitration Cases

๐Ÿ”น Meaning of Doctrine of Frustration

Under Indian Contract Act, 1872, a contract becomes void when:

  • Performance becomes impossible, or
  • Performance becomes unlawful after the contract is made

This is also called โ€œsupervening impossibility.โ€

๐Ÿ”น Key Elements of Frustration

For frustration to apply:

  1. Valid contract must exist
  2. Unexpected event occurs
  3. Event is beyond control of parties
  4. Makes performance impossible or radically different
  5. Not due to fault of either party

๐Ÿ”น Role in Arbitration

In arbitration:

  • Parties may claim frustration to terminate liability
  • Arbitrators decide whether the event:
    • Truly frustrates the contract
    • Or just makes it more difficult/expensive
  • If frustration is proven:
    • Contract is automatically discharged
    • No damages for non-performance

๐Ÿ”น Important Case Laws (At Least 6)

1. Taylor v Caldwell

  • A music hall was rented but burned down before use
  • Court held contract was frustrated due to destruction of subject matter
  • Established doctrine of impossibility

๐Ÿ‘‰ Principle: If the subject matter is destroyed, contract ends.

2. Krell v Henry

  • Room rented to view coronation procession of King Edward VII
  • Event was cancelled due to illness
  • Court held contract frustrated because purpose failed

๐Ÿ‘‰ Principle: Frustration of purpose applies.

3. Satyabrata Ghose v Mugneeram Bangur & Co.

  • Land development contract delayed due to war conditions
  • Supreme Court clarified that impossibility includes impracticability

๐Ÿ‘‰ Principle: Frustration is not limited to physical impossibility.

4. Energy Watchdog v CERC

  • Power companies claimed frustration due to rise in coal prices
  • Court rejected claim

๐Ÿ‘‰ Principle: Commercial hardship is NOT frustration

5. Alopi Parshad & Sons Ltd. v Union of India

  • Contractor claimed increased costs made contract impossible
  • Court held contract not frustrated

๐Ÿ‘‰ Principle: Increased expense โ‰  frustration

6. Naihati Jute Mills Ltd. v Hyaliram Jagannath

  • Contract affected by government control orders
  • Court held frustration applies only if performance becomes impossible

๐Ÿ‘‰ Principle: Legal restrictions may cause frustration, but not always.

7. Davis Contractors Ltd. v Fareham UDC

  • Construction took longer and cost more
  • Court held contract not frustrated

๐Ÿ‘‰ Principle: Mere delay or difficulty is insufficient.

๐Ÿ”น Application in Arbitration Proceedings

In arbitration disputes, frustration is commonly raised in cases involving:

  • Construction contracts
  • Infrastructure projects
  • Supply chain disruptions
  • Force majeure situations (e.g., pandemics, war)

Arbitratorโ€™s Approach:

  • Examine contract terms (especially force majeure clause)
  • Analyze whether:
    • Event was foreseeable
    • Risk was allocated
    • Performance truly impossible

๐Ÿ”น Frustration vs Force Majeure

BasisFrustrationForce Majeure
SourceLaw (Section 56)Contract clause
ControlAutomaticDepends on clause
EffectContract voidSuspends/terminates obligations

๐Ÿ”น Key Takeaways

  • Doctrine of frustration discharges contracts automatically
  • It is narrowly applied by courts and arbitrators
  • Mere hardship, delay, or loss is not enough
  • Frequently used as a defense in arbitration but rarely successful

LEAVE A COMMENT