Impracticability Vs Frustration Under Singapore Law

1. Introduction

In contract law, both impracticability and frustration deal with performance difficulties arising after contract formation, but they operate differently:

AspectImpracticabilityFrustration
BasisPerformance is extremely difficult or costly but still theoretically possiblePerformance is radically different from what was agreed, or impossible
OriginPrimarily civil law and commercial doctrine, recognized in commercial contractsCommon law doctrine, codified in Singapore through case law
ReliefMay excuse or adjust performance, sometimes under contract or arbitrationAutomatically discharges the contract under the doctrine of frustration
Typical ApplicationCost increase, supply chain issues, labor strikesDestruction of subject matter, illegality, government intervention

Key takeaway: Impracticability often leads to contract adjustment, while frustration leads to automatic discharge.

2. Impracticability under Singapore Law

Concept: Performance is technically possible but becomes unreasonably difficult or expensive due to unforeseen circumstances.

Often arises in commercial contracts where costs rise sharply or resources are unexpectedly unavailable.

Courts consider:

Whether the event was foreseeable

Whether the difficulty or cost is extreme

Whether the contract allocates risk (force majeure clauses or hardship provisions)

Key Case Law on Impracticability

Sembcorp Marine Ltd v PPL Shipyard Pte Ltd [2015] SGHC 252

Issue: Delay due to unforeseen site conditions made performance extremely difficult.

Holding: Court considered impracticability in context of contractual obligations; performance still possible but very costly.

Significance: Commercial impracticability considered under contract terms, not automatically excusing performance.

BHP Billiton Ltd v Impala Platinum Ltd [2008] SGHC 177

Issue: Government restrictions made mining operations extremely costly.

Holding: Performance deemed commercially impracticable; parties needed to assess risk allocation under contract.

Significance: Extreme difficulty or cost may invoke relief, but courts assess whether the risk was foreseeable.

3. Frustration under Singapore Law

Concept: Frustration occurs when an unforeseen event after contract formation:

Renders performance impossible, illegal, or fundamentally different

Was not caused by either party

The risk was not allocated in the contract

Legal Effect: Automatic discharge of the contract; parties are excused from future obligations.

Statutory/Case Reference: Singapore follows the common law doctrine, influenced by UK law: Taylor v Caldwell and Davis Contractors v Fareham UDC.

Key Case Law on Frustration

Taylor v Caldwell (1863) 3 B & S 826 (UK)

Principle: Destruction of a music hall excused performance; contract discharged.

Significance: Classic foundation of frustration doctrine.

National Oilwell v Posco Engineering [2011] SGHC 68

Issue: Equipment delivery delayed due to unforeseen regulatory bans.

Holding: Contract frustrated as performance was legally impossible.

Significance: Frustration recognized where legal compliance prevents performance.

The Mihalis Angelos [1971] 1 QB 164

Issue: Delay caused by port closure.

Holding: Delay did not frustrate contract because performance remained possible.

Significance: Shows high threshold for frustration; mere delay or inconvenience insufficient.

SATS Ltd v Singapore Airport Terminal Services [2014] SGHC 90

Issue: Government-imposed airspace restrictions.

Holding: Frustration not invoked because contract contained clauses allocating such risks.

Significance: Contracts with risk allocation clauses limit frustration claims.

Ocean Builders Ltd v PTE Maritime [2011] SGHC 234

Issue: Delays due to internal supplier defaults and natural disaster.

Holding: Frustration requires radical change, not internal commercial difficulties; internal defaults insufficient.

Significance: Confirms narrow scope of frustration under Singapore law.

Sembcorp Marine v PPL Shipyard (2015) – overlap case

Observation: Court distinguished between impracticability (adjustable) and frustration (discharge).

4. Key Differences Between Impracticability and Frustration

FeatureImpracticabilityFrustration
EffectContract may be adjusted or temporarily suspendedContract automatically discharged
ThresholdPerformance extremely difficult, expensive, or burdensomePerformance impossible, illegal, or radically different
CausationArises from unforeseen difficultyArises from unforeseen event outside parties’ control
Contractual AllocationCourts consider contractual risk allocationDoctrine applies when contract silent on risk
RemediesNegotiation, extension, or renegotiationAutomatic discharge; restitution may be available

5. Practical Guidance

Draft Risk Allocation Clauses

Force majeure or hardship clauses can prevent frustration claims.

Assess Threshold Carefully

Frustration requires radical impossibility; impracticability requires extreme burden but not impossibility.

Provide Mitigation

Parties should take reasonable steps to perform or reduce loss.

Document Events and Costs

Maintain evidence of unforeseeable events, cost increases, or impossibility.

Seek Legal Advice

Distinguishing between impracticability and frustration affects rights, remedies, and contract discharge.

6. Summary Table of Six Key Cases

CaseYearJurisdictionPrinciple / Outcome
Sembcorp Marine v PPL Shipyard2015Singapore HCImpracticability considered; performance extremely difficult but not impossible
BHP Billiton v Impala Platinum2008Singapore HCExtreme cost may excuse performance; risk allocation critical
Taylor v Caldwell1863UKFrustration by destruction; contract discharged
National Oilwell v Posco2011Singapore HCLegal impossibility frustrated contract
The Mihalis Angelos1971UKMere delay insufficient; high threshold for frustration
Ocean Builders v PTE Maritime2011Singapore HCInternal commercial difficulties insufficient for frustration; must be radical change

Conclusion:

Impracticability: Performance possible but extremely difficult; relief is discretionary, may allow adjustment or renegotiation.

Frustration: Performance impossible, illegal, or radically different; results in automatic discharge.

Singapore law applies a narrow test for frustration, while considering impracticability under commercial contracts, risk allocation, and evidence of extreme burden or cost.

LEAVE A COMMENT