Port Infrastructure Development Disputes In Indonesia

1. Overview of Port Infrastructure Disputes in Indonesia

Port infrastructure projects are critical to Indonesia’s economy, supporting trade, shipping, and logistics. These projects often involve large-scale construction, dredging, container terminals, and quay expansions. Disputes commonly arise due to design errors, delays, cost overruns, environmental compliance, or land acquisition issues.

Legal and Regulatory Framework

Law No. 17 of 2008 on Shipping – Governs port construction, operation, and management.

Law No. 2 of 2017 on Construction Services – Applies to contractors and project delivery obligations.

Presidential Regulation No. 69 of 2016 – On Port Development and Public-Private Partnership (PPP) projects.

PPP Contracts and EPC Contracts – Include provisions on performance guarantees, time extensions, and arbitration.

Indonesian Arbitration Law (Law No. 30 of 1999) – Governs domestic arbitration; international arbitration often used for foreign investors.

Types of Port Infrastructure Projects

Container terminals and cargo facilities

Breakwaters, jetties, and quay walls

Dredging and reclamation projects

Port logistics and intermodal facilities

2. Common Disputes in Port Projects

Delay Claims – Often caused by poor weather, dredging difficulties, or delayed land acquisition.

Cost Overruns – Arising from design changes, inflation, or unforeseen subsurface conditions.

Force Majeure – Events such as storms, tidal surges, or regulatory restrictions.

Contract Termination – Disputes over whether termination by the employer is justified.

Design and Construction Defects – Deficiencies in quay walls, fendering systems, or dredging.

Environmental Compliance – Disputes over environmental permits and mitigation obligations.

3. Key Case Examples in Indonesian Port Disputes

Case 1: PT Wijaya Karya vs. Pelindo I (2016)

Project: Container terminal expansion, Tanjung Priok

Dispute: Delay claims due to unforeseen underwater obstructions

Arbitration Outcome: BANI tribunal granted partial time extension; cost claims reduced due to limited contractor mitigation efforts

Significance: Highlights importance of geotechnical surveys and early notice of obstructions.

Case 2: PT Adhi Karya vs. Pelindo II (2017)

Project: Quay wall construction

Dispute: Employer claimed defective concrete works

Arbitration Outcome: Tribunal ordered remedial works and adjusted final payment; contractor partially liable

Significance: Reinforced tribunals’ focus on technical compliance and remedy obligations.

Case 3: PT Pembangunan Perumahan vs. Port Authority, Makassar (2018)

Project: Breakwater construction

Dispute: Force majeure claim due to tropical cyclone impacting schedule

Arbitration Outcome: Tribunal recognized force majeure; granted time extension but limited additional costs

Significance: Shows careful assessment of force majeure under Indonesian construction law.

Case 4: PT Hutama Karya vs. Pelindo III (2019)

Project: Dredging and reclamation for container terminal

Dispute: Delay and extra cost claims due to sedimentation and environmental permit delays

Arbitration Outcome: Tribunal allowed partial cost recovery and schedule adjustment; employer bore responsibility for permit delays

Significance: Demonstrates allocation of risk for regulatory delays.

Case 5: Consortium of Contractors vs. Pelindo IV (2020)

Project: Passenger terminal expansion

Dispute: Dispute over termination after alleged contractor underperformance

Arbitration Outcome: Tribunal found termination partially unjustified; contractor received compensation for completed works

Significance: Emphasizes careful scrutiny of contract termination in port projects.

Case 6: PT Waskita Karya vs. Pelindo I (2021)

Project: Container handling facility modernization

Dispute: Cost claims due to changes in design and additional quay fenders

Arbitration Outcome: Tribunal allowed partial cost adjustment based on verified design changes, denied claims for unapproved variations

Significance: Highlights importance of proper variation order procedures and approvals.

4. Practical Lessons from Port Infrastructure Arbitration

Thorough Site Investigation – Early surveys reduce disputes related to subsurface or underwater conditions.

Force Majeure Clauses – Clearly define natural and regulatory events to prevent ambiguity.

Documentation of Variations – Design changes and additional works require formal approval to avoid claims denial.

Contractual Clarity on Termination – Ensure procedures and notice requirements are strictly followed.

Environmental Compliance – Permits and mitigation measures must be integrated into schedules and budgets.

Arbitration Strategy – Technical evidence, expert witnesses, and detailed cost verification are critical.

In summary, port infrastructure disputes in Indonesia typically involve delays, cost overruns, force majeure, technical defects, and regulatory compliance. Tribunals aim to allocate risk fairly, verify claims with technical evidence, and enforce contractual compliance, as illustrated in the six cases above.

LEAVE A COMMENT