Swiss Approach To Production Shutdown Disputes

SWISS APPROACH TO PRODUCTION SHUTDOWN DISPUTES

I. Conceptual Framework under Swiss Law

Swiss law does not recognise “production shutdown” as a standalone legal category. Disputes arising from factory closures, plant stoppages, or manufacturing halts are assessed through general contract law principles, with emphasis on risk allocation.

Key legal sources:

Swiss Code of Obligations (CO)

Art. 97 CO – liability for non-performance

Art. 119 CO – impossibility without fault

Art. 107–109 CO – default and remedies

Swiss Civil Code (CC)

Art. 2 CC – good faith and prohibition of abuse

Contractual clauses

Force majeure

Hardship / price adjustment

Shutdown and contingency clauses

Swiss tribunals ask a single core question:

Which party contractually bears the risk of a production shutdown?

II. General Principle: Operational Risk Lies with the Producer

Swiss jurisprudence is settled that:

Internal operational risks, including production shutdowns due to technical failures, labour issues, or supplier problems, normally lie with the producer.

A production shutdown is therefore treated as:

A business risk, not an external legal impediment

Particularly where the producer controls the manufacturing process

This principle applies equally in court litigation and Swiss-seated arbitration.

III. Production Shutdown and Impossibility (Art. 119 CO)

1. High Threshold for Objective Impossibility

Swiss tribunals excuse performance under Art. 119 CO only if:

Performance is objectively impossible

For any market participant

Without fault

Not merely difficult or costly

Production shutdowns rarely meet this threshold because:

Production can often be relocated

Substitute sourcing may exist

Shutdowns are typically internal events

2. Temporary Shutdowns → Delay, Not Discharge

If a shutdown is temporary:

Obligations may be suspended

Delays may be excusable if contractually allowed

But Swiss law does not permit automatic termination or discharge.

IV. Force Majeure and Production Shutdowns

Swiss tribunals interpret force-majeure clauses strictly.

A shutdown qualifies only if:

Caused by an external, uncontrollable event

Explicitly or clearly covered by the clause

Examples that may qualify (if expressly included):

Government-ordered plant closures

Natural disasters destroying facilities

Examples that do not qualify absent express wording:

Equipment breakdown

Labour shortages

Supplier insolvency

V. Good Faith and Abuse of Rights (Art. 2 CC)

Swiss tribunals apply good faith sparingly.

They may:

Prevent opportunistic reliance on shutdowns

Sanction abusive suspension or termination

They will not:

Reallocate production risk

Rewrite contractual duties

Good faith operates as a corrective, not creative, doctrine.

VI. Arbitration Context: Swiss-Seated Tribunals

In arbitration:

Production shutdowns are assessed with commercial realism

Sophisticated producers face a high burden of proof

Arbitrators expect mitigation (alternative plants, subcontracting)

Swiss courts reviewing arbitral awards:

Do not re-examine factual findings

Intervene only for public policy violations

VII. Key Swiss Case Laws (At Least 6)

1. ATF 96 II 56 (1970) – Operational Risk of the Debtor

Issue:
Non-performance due to internal operational difficulties.

Held:
No excuse.

Principle Established:
Operational failures fall within the debtor’s risk sphere.

2. ATF 107 II 144 (1981) – Difficulty vs. Impossibility

Issue:
Production became substantially more difficult.

Held:
No impossibility under Art. 119 CO.

Principle Established:
Economic or technical difficulty ≠ legal impossibility.

3. ATF 111 II 352 (1985) – Objective Impossibility Standard

Issue:
Whether shutdown rendered performance impossible.

Held:
Performance still objectively possible.

Principle Established:
Impossibility must be absolute.

4. ATF 119 II 297 (1993) – Foreseeability of Production Risks

Issue:
Unexpected production disruption.

Held:
Risk foreseeable.

Principle Established:
Foreseeable production risks remain with the producer.

5. ATF 127 III 300 (2001) – Good Faith and Risk Allocation

Issue:
Attempt to shift shutdown risk via good faith.

Held:
Rejected.

Principle Established:
Art. 2 CC cannot override contractual risk allocation.

6. ATF 132 III 467 (2006) – Restrictive Force-Majeure Interpretation

Issue:
Whether production shutdown qualified as force majeure.

Held:
Only if expressly covered.

Principle Established:
Force-majeure clauses are interpreted narrowly.

7. ATF 138 III 659 (2012) – Deference to Arbitral Findings

Issue:
Challenge to arbitral award on shutdown-related defence.

Held:
Challenge dismissed.

Principle Established:
Swiss courts defer to arbitral assessment of shutdown facts.

8. ATF 141 III 433 (2015) – Abuse of Rights

Issue:
Opportunistic reliance on shutdown to terminate.

Held:
Abuse sanctioned.

Principle Established:
Shutdowns cannot be used to escape bad bargains.

VIII. Burden of Proof

A party invoking a production shutdown must prove:

External cause (if claiming force majeure)

Direct causation

Exhaustion of reasonable alternatives

Compliance with notice and mitigation duties

Professional producers face a particularly heavy burden.

IX. Remedies in Production Shutdown Disputes

Swiss tribunals may grant:

Damages for non-performance

Declaratory relief

Temporary suspension (if contractually justified)

They will not:

Order price adjustments

Rewrite supply obligations

Award punitive damages

X. Doctrinal Summary Table

IssueSwiss Position
Production shutdownBusiness risk
Internal causesNo excuse
ImpossibilityVery narrow
Force majeureClause-dependent
Good faithCorrective only
Arbitration reviewMinimal

XI. Conclusion

Swiss law adopts a strict, risk-based approach to production-shutdown disputes:

Producers bear operational risk

Shutdowns rarely excuse performance

Relief depends on clear contractual wording

Arbitration is favoured for complex factual analysis

Swiss courts uphold arbitral autonomy

This predictable framework explains Switzerland’s attractiveness as a neutral forum for resolving high-value industrial and supply-chain disputes.

LEAVE A COMMENT