Swiss Treatment Of Submarine-Cable Contracts.

SWISS TREATMENT OF SUBMARINE-CABLE CONTRACTS

I. Structural Context: Submarine-Cable Contracts as Global Infrastructure Agreements

Submarine-cable contracts typically involve:

System construction and supply agreements

Landing-party and consortium agreements

Capacity purchase (IRU) and lease contracts

Operation, maintenance, and repair (OMR) arrangements

Swiss tribunals treat these as complex, long-term infrastructure contracts with:

Heavy regulatory dependency

Multijurisdictional performance

Sophisticated risk-allocation mechanisms

Arbitration focuses on private-law obligations, not sovereign maritime or telecom regulation.

II. Arbitrability of Submarine-Cable Disputes Under Swiss Law

Under Art. 177 PILA, disputes are arbitrable if they concern economic interests.

Swiss tribunals accept arbitration over:

Construction delays and defects

Capacity-allocation and IRU disputes

Maintenance and repair obligations

Outage liability and service credits

Cost-sharing and consortium-governance conflicts

They reject arbitration only where a claim seeks to:

Override maritime or telecom licences

Bind coastal states or regulators

Adjudicate public-law permissions

III. Legal Characterisation of Submarine-Cable Contracts

Swiss tribunals generally characterise submarine-cable contracts as:

Atypical mixed contracts, combining:

Contract for work (Art. 363 ff. CO)

Continuing service obligations

Consortium-type cooperation duties

A defining feature is risk segmentation, especially for:

Marine hazards

Permit and landing risks

Seabed interference

Repair logistics

IV. Interpretation of Core Issues in Submarine-Cable Disputes

1. Construction and Installation Obligations

Swiss tribunals distinguish between:

Obligations of result (delivery of a cable system meeting specs)

Obligations of means (marine operations subject to risk)

Installation difficulties (weather, seabed conditions, third-party interference) do not constitute breach unless:

The contractor deviated from agreed standards, or

The contract allocated marine risk to the contractor

2. Regulatory and Landing-Permit Risks

Landing rights and coastal permits are treated as foreseeable regulatory risks.

Unless expressly guaranteed:

Permit delays or refusals

Changes in landing conditions

Do not excuse performance under Art. 119 CO.

Swiss tribunals enforce clauses allocating:

Permit-risk

Change-in-law consequences

3. Capacity Allocation and IRU Disputes

In capacity and IRU disputes, Swiss tribunals focus on:

Contractual definitions of capacity

Upgrade and reconfiguration rights

Restoration priorities after outages

Economic disappointment (e.g., congestion or latency) does not amount to breach absent:

Express performance benchmarks

4. Outages, Faults, and Repair Obligations

Cable faults are analysed through:

Contractual fault-management regimes

Agreed repair timelines

Liability caps and service-credit mechanisms

Swiss tribunals strictly enforce:

Exclusions for marine hazards

Force-majeure-type risk allocation

Total cable failure rarely justifies termination unless contractually defined as fundamental.

5. Consortium Governance and Cost Sharing

Consortium disputes are resolved by:

Strict interpretation of governance provisions

Enforcement of voting and cost-allocation rules

Swiss tribunals resist importing partnership-law analogies unless expressly agreed.

V. Role of Good Faith (Art. 2 CC)

Good faith plays a corrective but restrained role, particularly where:

A consortium member withholds repair consent

A landing party blocks access opportunistically

Outage responsibility is shifted strategically

Swiss tribunals may sanction abuse of rights but will not:

Reallocate agreed marine or regulatory risk

VI. Evidence and Technical Complexity

Submarine-cable arbitration is highly technical.

Swiss tribunals:

Freely assess marine-engineering, fault-analysis, and network-performance evidence

Appoint neutral experts where necessary

Do not defer automatically to:

Cable suppliers

Marine contractors

The tribunal’s task is to determine contractual compliance, not optimal engineering.

VII. Swiss Federal Supreme Court Review

The Swiss Federal Supreme Court:

Does not reassess technical fault causation

Does not reinterpret outage or IRU economics

Does not intervene due to harsh outcomes

Annulment is limited to:

Procedural irregularities

Ultra petita decisions

Breach of international public policy

This ensures finality in submarine-cable arbitration.

VIII. Key Swiss Case Laws (At Least 6)

These decisions, though not submarine-cable-specific, are consistently relied upon in disputes involving large-scale infrastructure contracts.

1. ATF 96 II 56 (1970) – Allocation of Infrastructure Risk

Held: Contractual risk allocation governs complex projects.
Application: Marine and permit risks lie where allocated.

2. ATF 107 II 161 (1981) – Foreseeable Technical Risk

Held: Foreseeable difficulties do not excuse performance.
Application: Seabed and weather risks are inherent.

3. ATF 111 II 352 (1985) – Objective Impossibility

Held: Only absolute impossibility triggers Art. 119 CO.
Application: Cable faults rarely meet this threshold.

4. ATF 119 II 297 (1993) – Burden of Proof

Held: Claimant must prove breach, causation, and damage.
Application: Outage claims require contractual deviation proof.

5. ATF 127 III 365 (2002) – Freedom of Contract

Held: Sophisticated parties may freely structure infrastructure risk.
Application: IRU and liability-cap regimes are upheld.

6. ATF 132 III 389 (2005) – Assessment of Technical Evidence

Held: Arbitrators have discretion in weighing expert reports.
Application: Conflicting fault analyses are freely evaluated.

7. ATF 138 III 659 (2012) – Limited Review of Arbitral Awards

Held: No review of technical or factual findings.
Application: Protects finality in cable disputes.

8. ATF 141 III 433 (2015) – Abuse of Rights

Held: Rights must be exercised in good faith.
Application: Prevents strategic obstruction in consortium operations.

IX. Practical Implications for Drafting and Arbitration

Swiss practice encourages:

Explicit marine-risk allocation

Clear outage and repair regimes

Defined IRU performance standards

Robust consortium-governance clauses

Arbitration clauses suited to multi-party disputes

Ambiguity is resolved objectively and commercially, not regulatorily.

X. Conclusion

The Swiss approach to submarine-cable contracts is characterised by:

Strict enforcement of contractual risk allocation

High thresholds for impossibility and termination

Deference to arbitral technical assessment

Minimal judicial interference

This makes Switzerland a highly reliable arbitral seat for resolving submarine-cable and global digital-infrastructure disputes.

LEAVE A COMMENT