Arbitration Regarding Rooftop Solar, Energy-Efficiency, And Battery-Storage Failures

1. Overview of Disputes in Rooftop Solar, Energy-Efficiency, and Battery Storage

Disputes in these sectors usually arise due to:

System Design Failures: Incorrect sizing of solar panels, inverters, battery systems, or energy-efficiency devices leading to underperformance.

Installation Defects: Improper mounting, electrical connections, or integration with existing electrical networks.

Equipment Failures: Defective solar panels, inverters, controllers, or batteries causing short circuits, energy losses, or safety hazards.

Operational Inefficiencies: Systems failing to meet guaranteed energy output, reduced efficiency, or faulty battery charge-discharge cycles.

Maintenance and Warranty Claims: Disputes over preventive maintenance, replacements, or warranty coverage.

Regulatory Non-Compliance: Violations of grid codes, fire safety norms, or local electrical regulations.

Performance Guarantees and Penalties: Failure to achieve contractual energy savings or power-generation targets.

Arbitration is commonly invoked due to:

Confidentiality of commercial disputes.

Need for technical expert evaluation.

Speedier resolution compared to courts.

2. Common Arbitration Issues

Performance Shortfall: Dispute over actual versus guaranteed energy generation or energy efficiency savings.

Design vs. Installation Liability: Determining whether failures are due to poor design, installation, or defective equipment.

Battery Storage Failures: Liability for fires, thermal runaway, or reduced lifespan due to improper integration.

Liquidated Damages: Claims due to delay in commissioning systems or failing to meet contractual energy targets.

Regulatory Compliance: Ensuring systems meet grid connection requirements, safety, and fire codes.

Apportionment of Liability: Particularly when multiple contractors, suppliers, and consultants are involved.

3. Illustrative Case Laws

Case 1: Rooftop Solar PV System Underperformance

Facts: A commercial rooftop solar project produced only 70% of the promised output. Owner claimed contractor breached performance guarantee.

Arbitration Finding: Tribunal found contractor partially responsible due to incorrect inverter sizing; panel quality also contributed. Contractor paid proportional damages and agreed to system optimization.

Key Principle: Performance guarantees are enforceable; causation and technical expert evaluation are critical.

Case 2: Battery Storage Fire Incident

Facts: Lithium-ion battery system caught fire in a commercial energy-storage installation. Owner claimed supplier failed to meet safety norms.

Arbitration Finding: Tribunal held supplier liable for non-compliance with IS/IEC battery safety standards and awarded damages for equipment replacement and downtime.

Key Principle: Suppliers must adhere to safety standards; negligent installation can trigger liability.

Case 3: Energy-Efficiency Retrofit Failure

Facts: A retrofit project promised 25% reduction in energy consumption but achieved only 10%.

Arbitration Finding: Tribunal found audit and implementation errors in energy-efficiency measures. Contractor liable for shortfall; awarded damages based on lost savings.

Key Principle: Energy savings guarantees are binding; measurable verification is essential.

Case 4: Delay in Rooftop Solar Commissioning

Facts: Project delayed due to late delivery of panels and incomplete installation. Owner sought liquidated damages.

Arbitration Finding: Tribunal apportioned delay between supplier (panel delivery) and installer (poor project management). Damages reduced accordingly.

Key Principle: Delay claims must account for contributory factors; partial liability reduces damages.

Case 5: Hybrid Solar-Battery System Malfunction

Facts: Hybrid system integrating solar PV with batteries failed to deliver stable power due to improper controller settings.

Arbitration Finding: Tribunal held installation contractor responsible for misconfiguration; equipment supplier not liable. Contractor reimbursed rectification costs.

Key Principle: Proper commissioning and configuration are part of contractor obligations.

Case 6: Warranty and Maintenance Dispute

Facts: Post-warranty, rooftop solar panels showed rapid degradation. Contractor denied liability citing normal wear and tear.

Arbitration Finding: Tribunal held contractor responsible for substandard panels and awarded replacement under extended warranty terms.

Key Principle: Warranty obligations cover defects beyond normal wear; expert testing determines defect versus normal degradation.

Case 7: Regulatory Non-Compliance Leading to Grid Rejection

Facts: Rooftop solar system rejected by utility due to non-compliance with grid interconnection standards. Owner claimed damages from contractor.

Arbitration Finding: Tribunal ruled contractor liable for failure to follow standards and awarded costs for rectification and delayed energy sales.

Key Principle: Compliance with regulatory and utility standards is a contractual obligation.

4. Key Takeaways

Expert Evaluation is Central: Technical experts in solar, battery, and energy-efficiency systems often decide the outcome.

Clear Performance Metrics Reduce Disputes: Contracts should specify energy output, efficiency savings, and battery cycles.

Liability Can Be Shared: In hybrid projects, tribunals may apportion responsibility among suppliers, installers, and designers.

Warranty, Maintenance, and Safety Are Critical: Post-installation failures often hinge on contractual maintenance obligations.

Regulatory Compliance Cannot Be Ignored: Non-compliance can lead to both contractual and legal liability.

LEAVE A COMMENT